HHFHidden Hills Fencing

Guide - Rules and permits

Fence height and the HCA permit process in Hidden Hills

Before you order a fence in Hidden Hills, one process governs everything: the HCA Architectural Committee review, which comes before the City permit. This guide lays out the baseline height limits and, in a clear table, the Committee stages and the timeline they add.

The short answer. Six feet at the sides and rear, roughly three and a half feet across the front, is the baseline any fence starts from. What actually decides the height, the material, and the look is the HCA Architectural Committee, which reviews every fence before the City of Hidden Hills will issue a permit. Give that review eight to sixteen weeks.

Height limits at a glance

Most guidance you will read quotes the City of Los Angeles limits. Those do not govern here. Hidden Hills is its own incorporated city, and its code sets no height limit for a perimeter fence at all: section 5-2C-4 leaves that to the Architectural Committee. What the code does settle is which structures need review, and that is the table worth having.

What the code settlesStandard
Perimeter fence heightNo figure in the code. Set by the Architectural Committee
Any solid fenceNever a minor structure, even under 6 ft, so always reviewed
Open fencing, side and rear setbackTreated as a minor structure
Solid wall in a side or rear setback3 ft or less, sited 15 ft or more from the line
Retaining wall in the front setback2 ft or less
Front setback pilastersUp to 54 in tall and 30 in wide

The open three-rail ranch fence that fronts most properties is reviewed for how it reads and sits against the trail easements rather than measured against a simple privacy-fence limit, which is why the frontage line in the table is a case-by-case review rather than a fixed number.

The HCA Architectural Committee process, stage by stage

This is the part that surprises owners used to building elsewhere: in Hidden Hills the Committee review is the real gate, and it comes before the City permit. The Hidden Hills Community Association Architectural Committee reviews every fence for material, massing, height, and how the line interacts with the horse-trail easements, and it is among the strictest reviews in California. Here is the sequence and the time each stage usually takes.

StageWhat happensTypical time
1. Design and submittalMaterial, height, massing, and easement setbacks drawn for the Committee1 to 2 weeks
2. HCA Architectural CommitteeThe Committee reviews and approves, or asks for changes8 to 16 weeks
3. City of Hidden Hills permitIssued after HCA approval, with Los Angeles County oversight1 to 3 weeks
4. Guard-gate scheduling and buildCrew and material cleared at the manned gate, then installdays

The eight to sixteen week Committee window is the number that sets your calendar, and a non-standard design can run longer. It is not a formality. A fence built without approval can be ordered changed or torn out, a bill that dwarfs the review it skipped. We draw the submittal to what the Committee approves and put that window on the schedule from day one.

When the City permit and other rules apply

After HCA approval, the City of Hidden Hills issues the fence permit, with Los Angeles County oversight in the background. A standard fence at the baseline height is routine at that stage. A few situations bring extra review: a fence taller than the baseline, a retaining wall that holds back soil on a graded lot, a barrier around a pool, or anything that touches a trail easement. Each is handled as part of the same submittal so nothing surfaces late.

A pool barrier has its own California standard, at least five feet with a self-closing, self-latching gate, and is inspected separately. The pool fencing page covers that code in full.

What we do about it on these lots

We treat the Committee as the first client. Nothing gets ordered until the material, height, and easement setbacks are drawn to the citywide standard, the submittal is assembled, and the price is set against a fence the Committee will pass. The City permit follows from that, and the crew clears the guard gate for the build. It keeps the project on schedule and off the Committee's change list. The cost guide sets out what each height and material choice does to the number, and the ranch rail page covers the frontage standard itself.

We can take the paperwork

The submittal gets drawn to the citywide standard, carried through the Architectural Committee and then the City permit, and priced as a fence that clears both. On-site estimate at no charge, no obligation.

Arrange a site visit